SEWER MAIN REPLACEMENT - WILLOW STREET
Posted on: March 10, 2023 - 10:28am

PA American will be replacing 809 feet of aging sewer pipe that was installed in the 1960's with 8-inch PVC pipe.
Work is planned to begin on or about the second full week of March and be completed by the end of May. Crews will be working 7 a.m. to 4 p.m., Monday through Friday.
Project contact is Jim Kelly 610.384.2872